General contractor · Mount Pleasant, SC
General contractor license requirements in Mount Pleasant, South Carolina
Everything a general contractor needs to work legally in Mount Pleasant: the South Carolina state rule and the local license. Checked November 7, 2026 from 11 official sources.
What does a general contractor need to work in Mount Pleasant?
You need two licenses: one from South Carolina and one from Mount Pleasant.
South Carolina state license · required
General Contractor license (Contractor's Licensing Board)
Mount Pleasant license · required
Contractor business license (rate class 8.1, NAICS 23)
- Mount Pleasant fee
- $50
- Mount Pleasant bond
- None listed
- South Carolina bond
- None listed
- Insurance
- Not listed
Steps to work as a general contractor in Mount Pleasant
- 1
Get the South Carolina General Contractor license (Contractor's Licensing Board)
A Contractor's Licensing Board license is needed to perform or offer to perform general or mechanical contracting when the total cost of construction is more than $10,000.45
More
The total cost of the whole project sets the license group, and it is unlawful to split work into smaller parts to avoid the license rules.
- 2
Apply for your Mount Pleasant license
$50Contractor business license (rate class 8.1, NAICS 23): $50 resident minimum on the first $2,000 of gross income (plus $2.11 per additional $1,000).2 Bring the bond and insurance certificate.
- 3
Pull a permit for each job
Building permit applications are submitted online through the town's OPAL portal.111
More
The town checks contractor license status with SC LLR, and some trades must show a current state license before a permit is issued. Trade permits (mechanical, plumbing, electrical, gas) are also applied for in the portal. To change contractors on a permit, the owner or contractor of record must first send a written release.
Mount Pleasant license details
Contractor business license (rate class 8.1, NAICS 23) General contractorResidential builder Fee$50 Bond—
Who needs it
What you need
All state and municipal qualification exam and trade license requirements must be met before the license is issued.2
All performance and indemnity bonds required by the Building Code must be filed and approved before the license is issued. Zoning permits must be obtained when required.2
Each contractor must post a sign in plain view on each job identifying the contractor.2
Each prime contractor must file a list of subcontractors furnishing labor or materials for each project.2
More
A general contractor may not deduct the value of work done by a subcontractor.
A contractor may choose a per-job license. The tax for the full contract amount is paid before work starts, and an amended report and added fee per $1,000 of contract value is filed for each new job.2
More
Per-job licensees file a statement of compliance with a revised contract estimate by each April 30 while the project continues.
Fees and bond
Renewal
Annual licenses run May 1 to April 30 and are due April 30. The town adds a late penalty of 5% of the unpaid tax for each month after the due date, up to 30% per year.23
More
Non-resident rates apply to contractors with no permanent place of business in the town; non-resident taxes and rates are doubled.
Every person or business doing business in the town needs a business license based on business activity and gross receipts.3
More
Fees are due before starting operations and each year by April 30. Applications and renewals go through the town's OPAL online portal.
South Carolina rules in short
State license
General Contractor license (Contractor's Licensing Board). Full South Carolina requirements
Job size limit
A Contractor's Licensing Board license is needed to perform or offer to perform general or mechanical contracting when the total cost of construction is more than $10,000.45
More
The total cost of the whole project sets the license group, and it is unlawful to split work into smaller parts to avoid the license rules.
State bond
No separate license bond is required. Instead of a financial statement, a general contractor may file a continuous surety bond equal to its group's net worth requirement: Group 1 $20,000, Group 2 $60,000, Group 3 $150,000, Group 4 $250,000, Group 5 $350,000.469
More
The bond lists the State of South Carolina as obligee and protects people harmed by the contractor's breach of a construction contract. Bonds payable to the Residential Builders Commission are not accepted by this Board.
Hiring a general contractor in Mount Pleasant?
What to ask for
A current South Carolina General Contractor license (Contractor's Licensing Board), the Mount Pleasant contractor business license (rate class 8.1, NAICS 23).
Doing the work yourself
An owner may act as their own builder on a one- or two-family residence for their own use, not for sale or rent, and must supervise the work.1
More
The owner must complete the Non-Licensed Owner's Intent to Build form and record it with the Charleston County Register of Deeds. Selling or renting within two years of completion is presumed to break the exemption.
Sources
11 official pages, checked November 7, 2026
- License Requirements · Town of Mount Pleasant · checked 2026-11-07
- Ordinance 25052, Chapter 110: Business Licenses (Exhibit A) · Town of Mount Pleasant · checked 2026-11-07
- Business License Division · Town of Mount Pleasant · checked 2026-11-07
- SC Code of Laws, Title 40, Chapter 11 - Contractors · South Carolina Legislature · checked 2026-11-06
- General Information · SC Department of Labor, Licensing and Regulation, Contractor's Licensing Board · checked 2026-11-06
- Licensure with the Board · SC Department of Labor, Licensing and Regulation, Contractor's Licensing Board · checked 2026-11-06
- SC Code of Regulations, Chapter 29 - State Licensing Board for Contractors · South Carolina Legislature · checked 2026-11-06
- Fees · SC Department of Labor, Licensing and Regulation, Contractor's Licensing Board · checked 2026-11-06
- Renew My License · SC Department of Labor, Licensing and Regulation, Contractor's Licensing Board · checked 2026-11-06
- SC Code of Laws, Title 40, Chapter 59 - Residential Builders · South Carolina Legislature · checked 2026-11-06
- Building Permits · Town of Mount Pleasant · checked 2026-11-07
Rules change. Confirm with the agency before you bid or start work. How we research