What does an electrician need to work in Shorewood?
You need one license, from Shorewood. Illinois has no state license for this trade.
Shorewood license · required
Contractor registration
- Shorewood fee
- $120
- Shorewood bond
- $10,000
- Illinois bond
- None listed
- Insurance
- Proof required
Steps to work as an electrician in Shorewood
- 1
Get your surety bond
$10,000Shorewood requires a $10,000 bond for this license.2
You pay a yearly premium, not the full bond amount. Estimate the cost
- 2
Get a certificate of insurance
A certificate of insurance made out to the Village of Shorewood: general liability $500,000 (general contractors and subcontractors); automobile liability $500,000 for general contractors and $200,000 for subcontractors; excess liability $2 million for general contractors and $1 million for subcontractors; and workers' compensation if applicable.2
- 3
Apply for your Shorewood license
$120Contractor registration: $120 annual registration fee (not required for irrigation, roofing, plumbing, fire suppression and fire alarm contractors).2 Bring the bond and insurance certificate.
- 4
Pull a permit for each job
Permit applications and contractor registrations can be sent by mail or email (permits@shorewoodil.gov), brought in person, or left in the drop box behind Village Hall.7
More
Incomplete submittals are not accepted. Payment is due when the permit is approved.
Shorewood license details
Contractor registration General contractorResidential builderElectricianPlumberRooferLandscaperDemolition contractor Fee$120 Bond$10,000
Who needs it
What you need
Contractors whose work needs a State of Illinois license must attach proof of that license.1
Irrigation, roofing, plumbing, fire suppression and fire alarm contractors attach a copy of their State of Illinois license only; bond, insurance and fee are not required for them. Roofing contractors must also attach a driver's license or state ID.2
Electricians attach a copy of an Illinois municipal electrical license earned by testing, plus the bond, insurance and fee required of other contractors.2
Incomplete applications are not accepted.2
Fees and bond
A signed surety (license and permit) bond made out to the Village of Shorewood: $10,000 for general contractors, $5,000 for subcontractors and $50,000 for wrecking contractors.
More
Not required for irrigation, roofing, plumbing, fire suppression and fire alarm contractors.
Insurance
A certificate of insurance made out to the Village of Shorewood: general liability $500,000 (general contractors and subcontractors); automobile liability $500,000 for general contractors and $200,000 for subcontractors; excess liability $2 million for general contractors and $1 million for subcontractors; and workers' compensation if applicable.2
Renewal
Illinois rules in short
State license
No state license. Cities or counties may license it. Full Illinois requirements
Hiring an electrician in Shorewood?
What to ask for
the Shorewood contractor registration, and a certificate of insurance.
Sources
7 official pages, checked November 6, 2026
- Contractor Registration · Village of Shorewood · checked 2026-11-06
- Contractor's Registration Application · Village of Shorewood Building Department · checked 2026-11-06
- Illinois Municipal Code (65 ILCS 5), full text · Illinois General Assembly · checked 2026-11-06
- Bill Status of SB2307, 104th General Assembly (Electrician Licensing Act) · Illinois General Assembly · checked 2026-11-06
- IDFPR | Professions and Industries Regulated by IDFPR · Illinois Department of Financial and Professional Regulation · checked 2026-11-06
- 83 Ill. Adm. Code Part 468, Distributed Generation Installer Certification · Illinois General Assembly, Joint Committee on Administrative Rules · checked 2026-11-06
- Building Department · Village of Shorewood · checked 2026-11-06
Rules change. Confirm with the agency before you bid or start work. How we research